You have a pay-as-you-go Azure subscription that contains the virtual machines shown in the following table.
You create the budget shown in the following exhibit.
The AG1 action group contains a user named [email protected] only.
Use the drop-down menus to select the answer choice that completes each statement based on the information presented in the graphic.
Hot Area:
Correct Answer:
Box 1: VM1 and VM2 continue to run The Budget’s scope is RG1, so only VM1 will be handled. When the budget thresholds you’ve created are exceeded, only notifications are triggered. To stop resources, you need to setup additional things, none of which are mentioned in the question.
Box 2: one email notification will be sent each month.
Budget alerts for Resource Group RG1, which include VM1, but not VM2.VM1 consumes 20 Euro/day. The 50%, 500 Euro limit, will be reached in 25 days, and an email will be sent.
The 70% and 100% alert conditions will not be reached within a month, and they don’t trigger email actions anyway.
Credit alerts: Credit alerts are generated automatically at 90% and at 100% of your Azure credit balance. Whenever an alert is generated, it’s reflected in cost alerts and in the email sent to the account owners. 90% and 100% will not be reached though.
Reference: https://docs.microsoft.com/en-us/azure/cost-management-billing/costs/cost-mgt-alerts-monitor-usage-spending